July 2024

Background

ENERGY CHRONICLE



The amount of electricity that had to be redispatch through bottlenecks increased by a further 1,162 GWh in 2023 compared to the previous year. Nevertheless, the total costs were 37 percent lower. Of course, this was only because the exorbitant price level of 2022 had since returned to something like normal. A closer look, however, shows that the costs per gigawatt hour have also risen by around 42 percent since 2019.

The stock market fiction of a congestion-free grid is putting increasing pressure on electricity prices

(ref. 240704 /240705

Last year, 34,297 gigawatt hours of electricity clogged the bottlenecks in the German grid. To ensure that it still reached its destination, complex grid management was required, known as “redispatch,” which incurred additional costs of over three billion euros. Despite the grid expansion measures that have been initiated, a further increase in grid bottlenecks and redispatch costs is to be expected. Against this backdrop, a public debate has now arisen about possible further adjustments of the German electricity trading zone to physical realities through the introduction of local prices at certain grid nodes (240705). To better understand this current controversy, we will take a look at how the issue has developed to date.

Grid costs are rising steadily, even though electricity consumption is no higher than in 1990

The grid problem has been chronic for a long time and there is no sign of a quick fix. The three major HVDC lines, A-Nord/Ultranet, SuedLink, and SuedOstLink, which are intended to directly connect northern and southern Germany with a total capacity of 10 gigawatts, will not be available until the end of the decade. According to current plans, the eight other HVDC lines, some of which will also bridge existing grid bottlenecks in an east-west direction, are not expected to be completed until between 2032 and 2037 (240310).

However, bridging grid bottlenecks with HVDC power highways is not enough. The downstream three-phase transmission grid and distribution grids also require many changes. It is not only laypeople who wonder how this huge need for grid expansion could have arisen in the first place and whether there are simpler solutions. After all, Germany's gross electricity consumption last year was 525.5 terawatt hours, which was even lower than in 1990, when it was 549.9 TWh. Even the average for these 34 years since reunification was only 580 TWh (240308). Can it really be so difficult to supply a country with such constant electricity consumption without grid bottlenecks?

Energy policy focused solely on natural gas power plants instead of storage technologies

The answer is yes. Unfortunately, it has become so difficult because, a quarter of a century after the liberalization of the energy market, the grid is being strained in a completely different way than before. This is not only due to electricity trading, which did not exist in this form in the past. A whole range of factors come together on both the generation and demand sides. For example, it is no longer just the load curve that fluctuates, with power plants having to follow its peaks and troughs with their electricity generation in order to maintain the balance between consumption and generation. An ever-increasing proportion of electricity generation has also become fluctuating, as it is only available depending on wind or sunlight. Although this does not prevent an electricity supply based entirely on renewable energies, as is often claimed, it does require suitable technologies that have been criminally neglected in recent decades. Energy policy has focused one-sidedly on natural gas power plants as an accompanying technical measure instead of storage and energy conversion technologies for green electricity (210506). Above all, there was a failure to pursue from the outset the electrolytic conversion of surplus wind and solar power into hydrogen, which can serve as a storage medium and absolutely clean fuel for the gas-fired power plants that are still needed.

Grid congestion costs have increased eighteenfold since 2011

However, an even greater mistake was to give priority to unrestrained electricity trading within the EEX exchange zone over an increasingly overloaded grid structure. Instead of adapting the electricity market design to physical realities, the opposite was done, with billions spent on straining and bending the grid technology so that it could still be forced into the Procrustean bed of the exchange's fiction of a congestion-free grid.

Initially, all of this was still in a legal gray area because politicians largely left it to economic actors to set the rules of the game. This allowed the EEX electricity exchange to decree a uniform wholesale price for Germany/Austria/Luxembourg without taking grid conditions into account. Initially, there was also no legal basis for so-called redispatch, which appeared to overcome the sudden and rapidly worsening grid bottlenecks. Rather, it was a matter of voluntary agreements between transmission system operators and power plant operators. The resulting costs amounted to around €60 million in 2007. However, they doubled to more than €120 million in 2011, even though the redispatch volume was significantly lower than in 2007. This was because power plant operators had a stronger negotiating position than grid operators and were able to exploit this by driving up the specific costs per redispatch megawatt hour by more than double (see the 3 charts from November 2012).

The Federal Network Agency then issued a binding set of rules for the technical implementation and financial compensation of such redispatch measures, which came into force at the end of 2012 (121109). This explicitly obliged power plant operators to perform redispatch and capped their profits per megawatt hour. At the same time, the stock market fiction of a congestion-free grid was officially recognized and financially secured for the first time. This was not only a great gift for the EEX. Power plant operators also benefited in the long term from this new construction, even though they initially did not want to accept the curtailment of their market-based profits and had threatened to take legal action.

The legally enshrined regulation now made it possible to pass on all grid congestion costs to electricity consumers via grid fees. In addition to conventional redispatch, this included countertrading, compensation for the “outage work” of curtailed renewable electricity (161213), and the costs of the newly introduced “grid reserve” (130605). These total costs amounted to a modest €181 million in 2011. By 2023, however, this had risen to €3.2 billion. That was approximately eighteen times as much (see Figure 2).

Redispatch is essentially not a “forwarding,” but a costly "reshipment"

It is primarily the wind power generated in northern Germany and off the coast that fails due to grid bottlenecks. More precisely, it has to be curtailed because there is not enough demand in the immediate vicinity of where it is generated, but it also cannot reach the main consumption centers in the south, where it would certainly be needed. This is not particularly bad for the producers, as they have to be compensated for the forced “downtime.”

This is one side of the coin of what is known as “redispatch,” which means ‘forwarding’ or “resending,” with the latter term being closer to the truth. The curtailed amount of electricity is not forwarded at all, but rather regenerated behind the bottleneck by gas or coal-fired power plants located there increasing their output accordingly. This other side then naturally incurs additional costs, because the power plant operators do not do this for free. But it must be added that they are not unhappy to do so, because redispatch is just as important a source of income for them as compensation for outage work is for wind farm operators.

In concrete terms, last year this meant that 34.3 terawatt hours of electricity were covered by “grid congestion management,” which also includes the provision and use of grid reserves and “countertrading” as a commercial variant of redispatch. The costs for this amounted to €3.1 billion (see Figure 1). At 9.7 terawatt hours, wind power was by far the most curtailed energy source, while compensation was generally provided by gas-fired power plants (5.5 TWh) and hard coal-fired power plants (3.2 TWh).

The costs of this stock market fiction are passed on to electricity consumers via grid fees

Of course, this billion-dollar game of musical chairs can only work because it is provided for in the current electricity market design and the resulting costs can be passed on to electricity consumers via grid fees. One of the beneficiaries is the Leipzig-based electricity exchange EEX with its subsidiary EPEX Spot in Paris, which, more than two decades ago, rather arbitrarily introduced a uniform wholesale price for its zone, which included Austria and Luxembourg in addition to Germany. The model for this was unmistakably the dream of a “European copper plate,” which electricity traders and other electricity managers with no technical background were quite unabashed about at the time, while for experts it was more of a nightmare—especially since for them the metaphor “copper plate” conjured up the vision of a Europe-wide short circuit (170310).

But even the well-developed German electricity grid, which until liberalization served only to supply households, businesses, and industry with electrical energy, was by no means capable of handling unlimited loads. The same was true of Germany's grid interconnection with Austria and Luxembourg, which for historical reasons was closer than at other borders. The stock market fiction of a cross-border trading zone without grid bottlenecks was therefore bound to lead to an increasingly costly conflict with the reality of the grid technology as liberalization and electricity trading progressed. And, of course, to a corresponding increase in grid costs.

“Use instead of regulate” according to Section 13k EnWG does virtually nothing to change the problem

In this respect, Member of Parliament Ralph Lenkert was right when, in November last year, he rejected the insertion of the new Section 13k into the Energy Industry Act on behalf of the Left Party faction in the Bundestag, which has since shrunk to a “group.” Although the section has the promising title “use instead of curtail,” but is basically just another rather costly patchwork solution. “I want this federal government to start thinking,” said Lenkert. “Then it would finally introduce several electricity bidding zones instead of spending €5.5 billion on a single electricity bidding zone that only benefits large corporations in southern Germany.”

However, even among critics of the current electricity market design, there is disagreement as to whether dividing the uniform EEX trading zone into several bidding zones would be the best solution. Three years ago, a white paper entitled “Electricity Spot Market Design 2030 - 2050” (PDF) was published by twenty authors and several research institutes, which recommended the gradual introduction of location-based marginal prices instead of dividing the market into several price zones. “Frequent zone splitting is associated with recurring political debates and short- and long-term instabilities that affect, for example, the basis for financial contracts,” the authors pointed out. “In addition, establishing stable price zones is a major challenge with the increasing share of decentralized and renewable energy sources.”

This chart illustrates how grid congestion costs multiplied between 2013 and 2023. It also shows how the costs for conventional redispatch (blue) declined for two years after the dissolution of the German-Austrian electricity trading zone in 2018, but were offset by an increase in compensation for “outage work” by wind turbines (yellow). The subsequent shifts in the cost spectrum were due to “redispatch 2.0” and the gas price crisis that culminated in 2022 (231009).

(Note: The individual values given for 2022 and 2023 were only available in rounded form, which is why their sum differs upwards or downwards from the total costs shown in Figure 1.


Monopoly Commission advocated for at least two price zones in Germany as early as 2011

It remains noteworthy that the neoliberal-oriented Monopoly Commission advocated for the introduction of price zones in Germany as early as 2011. In its third special report pursuant to § 62 EnWG, it considered it economically wrong to try to eliminate grid bottlenecks solely by building new high-voltage lines. It feared that the resulting costs could outweigh the benefits. As an alternative, it proposed the introduction of at least two price zones in Germany. Power plants and electricity traders would then no longer be able to feed their supplies into the transmission grid from any point at the same price. Instead, the electricity to be transported would be auctioned together with the available transmission capacity. In the event of bottlenecks between the price zones, electricity supplies from outside would thus be more expensive than those fed into the price zone. These price differences could encourage power plant operators to build new plants primarily in areas of high consumption. This would avoid the need to build new transmission lines to bring electricity from power plants located far from consumption centers and increase grid stability (see Background, September 2011).

The Federal Network Agency, however, did not think much of such proposals. “The discussion about creating several wholesale price zones for electricity in Germany jeopardizes the planned grid expansion and harms competition in Germany and Europe,” it stated harshly in October 2011 (111011). It referred to the results of an expert opinion it had commissioned to counter corresponding plans by the EU Commission. This report also explicitly rejected the currently discussed separation of Austria from the EEX trading zone. Five years later, the agency had to give up its resistance on this point at least and call on the German transmission system operators to prepare for Austria's separation (161016).

Ring flows forced the dissolution of the German-Austrian electricity trading zone in 2018

The separation of Austria from the EEX trading zone was the first and so far only adjustment of the electricity market design to the actual physical load on the grid. It resulted from the fact that, starting in 2012, Poland and Czechia no longer wanted to make their interconnection points with the German electricity grid available without restriction (120102). The reason for this was the bottlenecks in the German grid connections with Austria, which led to ring flows via the grids of these two countries and jeopardized the stability of their transmission grids. The national grid operators therefore felt compelled to take technical defensive measures, which were also supported by the European regulatory authority ACER (150907, 170904, 180112). These ring flows mainly consisted of wind power generated in northern Germany, most of which could not reach Austria via the regular routes due to grid bottlenecks.

The Austrian economy in particular was strongly opposed to the dissolution of the cross-border electricity price zone at the time (161102). However, it became increasingly clear that there was no way around it because international pressure was simply too great and the defensive measures against ring flows were putting even more strain on the bottlenecks in Germany (170501). As of October 1, 2018, only Luxembourg remained in the EEX trading zone alongside Germany. The separation decided by ACER just under a year earlier went off without a hitch, with the wholesale price for Austria now, as expected, higher than that for the remaining Germany/Luxembourg zone (181003). This reached another peak in November 2018 with an hourly weighted average price of €56.68/MWh, but then fell to an unprecedented low of €14.51/MWh by April 2020. This is a fantastically low price when you consider that in June 2024, the “Phelix base” was still at 77.26 euros/MWh, after having skyrocketed to 465.18 euros two years earlier.

As a precaution, the German government decreed a “uniform electricity bidding zone” for Germany

Parallel to the debate about the dissolution of the German-Austrian trading zone, there was already discussion at that time about whether it would not also be appropriate to further divide the remaining zone within Germany, which would have to run roughly along the Main River line. The Austrian side even considered this to be a matter of urgency, because the actual grid bottlenecks were not the German-Austrian interconnection points, but rather between northern and southern Germany. However, the incentive to act on this matter was weaker because there was no international pressure. In addition, in November 2017, the German federal government at the time decided to amend the Electricity Grid Access Ordinance, which since then has expressly stipulated a “uniform electricity bidding zone” within Germany through the newly inserted § 3a (171101). In doing so, it wanted to prevent the remaining EEX trading zone from being redrawn in a quasi-technocratic manner by the EU Commission, regulatory authorities, and transmission system operators following the already scheduled dissolution of the German-Austrian trading zone.

As an alternative to further divisions of the EEX trading zone, a nodal pricing system was proposed back in 2015, which is now causing heated debate

However, there were also justified doubts as to whether such a division of the trading zones would be sufficient and would not have too many negative effects. At the time, the German Institute for Economic Research (DIW) already took the view that “targeted, congestion-oriented pricing for the entire German electricity system” would be the better solution (150907). This referred to a so-called nodal pricing system, as now called for by twelve energy economists in an article published on July 10 in the business section of the Frankfurter Allgemeine newspaper under the headline “The German electricity market needs local prices.” Among other things, the article stated the following as justification:

"Redispatch repairs rob Germany of the efficiency and effectiveness of market-based price control. So instead of laboriously and incompletely repairing market intervention with its resulting physically impossible decisions, the way should be cleared for electricity prices that balance supply and demand regionally and thus reflect the local value of electricity. The electricity price on the exchange should be higher where demand is high and lower where there is currently an oversupply. These conditions change every minute, so that price differences vary dynamically. Based on such prices, power plants, storage facilities, imports and exports, and intelligent electricity consumption can be optimized to benefit the grid and reduce average electricity costs."

Instead of the previously uniform nationwide wholesale price, the authors therefore consider local prices to be necessary, which reflect the physical and economic reality, rather than adapting this reality to the electricity exchange fiction of a congestion-free grid at a cost of billions. Basically, their view is consistent with the aforementioned research paper “White Paper Electricity Spot Market Design 2030 - 2050,” but it has now triggered an incomparably greater response. This is likely due to the fact that this “white paper” was only published in English, even though it ultimately concerned the German electricity market design, was predominantly written by German authors and research institutes, and was funded by the Federal Ministry of Education and Research. Even among experts, the willingness to translate 61 pages of scientific Esperanto from English was probably not particularly high.

Eleven trade associations and three trade unions categorically reject further corrections to the EEX trading zone

However, this changed completely after the same view of things was presented in a nationwide daily newspaper under the headline “The German electricity market needs local prices,” which was easy to understand and even provocative to some. No fewer than eleven trade and industry associations (see 240705) reacted immediately and rather allergically to this article with a “Joint appeal by leading trade associations to preserve the German electricity bidding zone” (PDF). This appeal was essentially identical to a statement published on July 20, also in the business section of the “Frankfurter Allgemeine”. What was new here, however, was that the eleven trade associations were now also supported by the German Trade Union Confederation (DGB) and its leading individual unions IGM, IGBCE, and Verdi. Accordingly, the introduction stated:

"Trade unions and trade associations jointly warn against the division of the unified German electricity bidding zone. The negative effects on the real economy are incalculable and outweigh any advantages."

That was essentially the gist of the entire statement, because the disadvantages and risks that were subsequently put forward are highly debatable. Ultimately, it remains a question of weighing up whether the advantages or disadvantages outweigh each other in this dispute over rather complicated economic and technical issues in theory. In principle, proponents of a nodal pricing system should acknowledge and keep in mind certain disadvantages and risks of their preferred method, just as the trade associations avoided dismissing the “nodal pricing” they rejected as fundamentally unsuitable in their statement. They were right to do so, because local prices at certain network nodes or regional electricity price zones are nothing new. Rather, they are proven means of bringing the flow of electricity into line with the technical conditions of the grid in liberalized markets. They have therefore long been in use in the US and also in several European countries.

The joint statement by trade associations and unions in the FAZ was titled “The energy transition needs a stable foundation.” Everyone will certainly agree with this platitude. In this case, however, it sounds more like: “Just don't touch it, because it could get even worse.” In any case, the current foundation is not stable.

Links (internal)

on grid bottlenecks and redispatch

on the dissolution of the German-Austrian electricity price zone

Links (external, without guarantee)